| Issues
of Interest Water
Supply
|
|
| Our Goal: To improve the livability of Florence through public education and community involvement. | |
| To: | Linda Locke; Leigh Deinert; Clarence Lysdale; Dave Franzen; Zane Ziemer; and Richard Walker |
| From: | Mayor Alan Burns |
| Date: | April 2, 2001 |
| Subject: | Answers to questions on Wellfield and Water Treatment Plan(t) Expansion |
Thank you for taking the time to ask questions about the city’s water treatment plant expansion. It is extremely important for council and staff to have the input from citizens.
Enclosed is a copy of the responses to your questions regarding the wellfield and water treatment plant expansion from Public Works Director Ken Lanfear.
If you have further questions, you can call me at my office at 997-3416, or contact my secretary, Barbara Miller at 997-3437.
Again, thank you!
Responses to questions contained in the following letters are summarized
below. To avoid
duplication, questions and responses have been grouped according to
general categories.
Linda L. Lock, President, Greentree Village, Inc. February 27, 2001
Leigh Deinert, February 28, 2001
Clarence A. Lysdale, March 1, 2001
Dave Franzen, March 1, 2001
Zane Zeimer, President, Citizens For Florence, February 28, 2001
Unsigned, February 15, 2001
Unsigned, February 26, 2001
Richard S. Walker, February 26, 2001
Dave Franzen, February 26, 2001
Heceta Water District
Water Demand
Wellfield
Schedule
Financial
Treatment Plant
Miscellaneous
Q. Does the City have an agreement to continue purchasing water
from HWD?
A. The Council is taking steps to negotiate such agreement.
Q. Is there an agreement between the City and Heceta Water District
for HWD to provide water to the proposed Sand Dune and Morales annexations?
A. The City does not plan to remove these properties from HWD
at this time. Agreement for future withdrawal will be a subject for
negotiation between the Council and HWD.
Q. Why were average demand values used to determine water facility
capacity requirements instead of peak day demand values?
A. Average demand values were not used to determine capacity
requirements. Based on historical water use, a peak demand value
of 330 gallons per day per person was assumed. The peak demand value
was computed by using the average value of 188 gallons per day per person
multiplied by a 1.75 peaking factor.
Q. Why is the projected demand presented during the February
26th City Council work session different than that contained in the 1998
Water Facilities Plan?
A. Current projected water demand differs from that contained
in the 1998 Facilities Plan for three reasons:
2. 1998 projections included an allowance for 0.9 million gallons per day of fire flow. Emergency storage for fighting fires is provided by the City’s storage reservoirs. As such, the City does not need treatment capacity to supply this instantaneous demand.
3. Year 2000 population projected in the 1998 Facilities Plan was 7,346. Actual population was about 7,236. (2000 census announced last week.)
Q. Why is the City expanding the current wellfield and treatment
plant if future demand will soon exceed that provided by the expansion
work?
A. It is most cost effective to maximize production capacity
of the existing treatment facility and wellfield before constructing separate
facilities.
Q. Why does the City want to expand net water treatment capacity
to 3 million gallons per day if demand will not reach this level until
2008?
A. Water demand is expected to exceed treatment capacity by
summer 2002. Because it is not cost effective to increase capacity
in very small increments, capacity would exceed demand until about 2008.
The planned expansion will bring the wellfield and treatment facility to
its maximum capacity.
Q. What will be the impact on water demand should below average
rainfall occur?
A. Water demand could rise because of increased irrigation.
However, during periods of low
rainfall, conservation measures should be encouraged by the City to
minimize increases in water demand. For example, Governor Kitzhauber
has already placed the state on notice that water
conservation measures would be necessary in response to the expected
drought this year.
Q. Why were population figures used for demand projections in
the Council work session non
consistent with those of the Comprehensive Plan Update?
A. Population figures presented during the Council work session
were the latest numbers available.
Q. The 1998 Sewer Rate and Connection Fee Study states that year
2000/2001 wastewater flow was projected to be 956,000 gallons per day.
The report also states that between 80 and 90% of water usage ends up at
the wastewater plant. If this is true, total water use in 2000/2001
should have been between 1,195,000 and 1,062,000 gallons per day.
Does the City really need to be able to produce 2 million gallons per day
for 2000/2001?
A. Yes. Design capacity for water treatment facilities
is based on maximum day demand. The
demand calculated using projected wastewater flow is an average for
the year. Florence has a
maximum to average day peaking factor of 1.75. Multiplying this
by the average demand values above yields water demand values between 2,091,250
and 1,858,500 gallons per day.
Q. What is the anticipated production capacity of the existing
wells following rehabilitation given that historical production has been
about 130 gallons per minute per well?
A. Following rehabilitation and assuming implementation of an
on-going wellfield maintenance
program, average production capacity is expecte4d to be 220 gallons
per minute per well.
Q. What is the anticipated long-term production capacity of the
new wells?
A. Assuming implementation of an on-going wellfield maintenance
program, average production capacity is expected to be 220 gallons per
minute per well.
Q. Will there be an impact on well production capacity if the
water table drops?
A. Well production capacity can be influenced by water table
elevation. However, minor elevation changes should not impact well
production. In order to significantly impact production a major drop
in water table elevation would have to occur.
Q. Will there be an impact on well production capacity if the
acidity of rainwater increases?
A. There should be no measurable impact on wellfield production
capacity should the acidity of rainwater increase.
Q. Will the City make available a copy of the wellfield test
report for public review?
A. Yes. A copy of the report will be made available for review.
Q. Following rehabilitation of the existing wells, will the City
provide the public access to daily well production figures?
A. Yes. Daily plant production figures are maintained now.
Q. Was the City Council told of the drop in well production prior
to its decision to sever ties with Heceta Water District?
A. The decision to eliminate reliance on Heceta Water District
was not based on the City’s water production capacity. Rather, it
was based on Heceta Water District’s inability to provide water to the
City beginning the summer of 2002 because of recent limitation set on Heceta’s
water withdrawal from Clear Lake.
Q. Are wells 1, 2 and 6 currently producing water?
A. Yes.
Q. Why is the City constructing new wells instead of maintaining
the existing wells?
A. The City has initiated an intensive rehabilitation effort
to optimize production from existing wells. However, even with increased
production from the existing wells, the resulting capacity will not be
great enough to meet projected City demand with the loss of Heceta Water
District as a reliable source of additional water starting in the year
2002.
Q. What is the life expectancy of the new wells?
A. The new wells should have life expectancies measured in terms
of decades. The City has working wells that have been in service
for in excess of 20 and 30 years.
Q. Will construction of the new wells be competitively bid?
A. Yes. new well construction will be competitively bid.
Q. What is the status of purchasing land needed for the wellfield
expansion?
A. The City is currently beginning negotiations for securing
land needed for the wellfield expansion.
Q. What is the alternative if the wells do not produce adequate
water (220 gallons per minute each)?
A. Additional wells could be installed as long as total production
did not exceed that allowed by the City’s water use permit.
Q. What “biocide” will be applied as part of the proposed wellfield
maintenance regime?
A. Sodium hypochlorite, concentrated chlorine bleach, will be
used periodically to control iron
bacterial within the wellfield.
Q. What is the current schedule for expansion of the wellfield
and water treatment plant?
A. Expansion of the City’s water treatment facilities is scheduled
for completion prior to summer 2020.
Q. Why is the current schedule different from others given in
the past?
A. The current schedule is essentially the same as past schedules
with the main goal being that of increased water production prior to summer
2002.
Q. Why is the City not following recommendations made in the
executive summary of the 1998 Water Facilities Plan?
A. The City is essentially following the 1998 Plan. The
recommended alternative outlined in the executive summary of the 1998 Water
Facilities Plan is no longer possible due to recent limitations placed
on water withdrawal from Clear Lake. However, the 1998 Plan recognized
that construction of a new surface water treatment plant on Clear Lake
might not be possible and recommended expansion of the City’s existing
facilities should this prove to be the case.
Q. Why has the 1998 Water Facilities Plan not been updated to
reflect the change in recommended expansion alternative.
A. It is not necessary to update the 1998 Plan since the City
is following recommendations contained in the Plan.
Q. What steps will be taken to protect groundwater at the future
(2008) wellfield site?
A. A wellhead protection program will be developed.
Q. How much land will be required for the future wellfield anticipated
to be developed by the year 2008?
A. The amount of land required for a future wellfield was conservatively
estimated at 300 acres in the Water Facilities Plan. Exact land requirements
will be determined during design of the future wellfield.
Q. How is the wellfield and water treatment plant optimization
work being funded? How will it
impact water rates?
A. Optimization work is primarily being funded by system development
charges (SDC’s). There will be no impact on water rates.
Q. How is the wellfield and water treatment plant expansion work
being funded? How will it impact water rates?
A. Expansion work is primarily being funded by system development
charges (SDC’s). There will be no impact on water rates.
Q. What will be the cost of an on-going wellfield maintenance
program?
A. An on-going wellfield maintenance program will cost an estimated
$40,000 per year.
Q. How much of the cost of wellfield and treatment plant optimization
is attributable to providing water for growth?
A. Wellfield and treatment plant optimization (bringing the
production rate to 2 mgd) is being done to meet current water demand.
Q. How much of the cost of wellfield and treatment plant expansion
is attributable to providing
water for growth?
A. All of the cost associated with expansion from 2 mgd to 3
mgd is attributable to providing for growth.
Q. What will be the total cost of the future wellfield construction
(year 2008)?
A. The 1998 Water Facilities Plan estimated that the future
wellfield would cost about $11.5 million and would have a net treatment
capacity of 4.7 million gallons per day.
Q. How will the future (2008) water facilities construction be
paid for?
A. Future water facilities construction will be funded by system
development charges.
Q. How much of the future (2008) expansion work is attributable
to providing water for growth?
A. All of the cost associated with future (2008) expansion is
attributable to providing for growth.
Q. How will future (2008) expansion work affect water rates (property
taxes)?
A. Future expansion work should not impact water rates or property
taxes.
Q. What deficiencies within the treatment plant have caused lower
than expected water production?
A. Deficiencies within the existing treatment plant have included
the following:
Q. What is being done to increase production capacity of
the existing water treatment plant?
A. The following steps have been or will be taken to improve
treatment plant performance:
Q. Why is the City moving ahead with plans to expand the
treatment plant and wellfield prior to proving that 2 mgd net water production
can be attained?
A. Due to the reduction in Heceta Water District’s ability to
provide water, the City needs increased production capacity by the summer
of 2020. Because of the short time line, the City cannot wait until
the end of summer 2001 to move forward with plans for expanding its water
facilities. Public bidding, equipment delivery and construction of
the treatment plant expansion will require about 9 months.
Q. What is the expected treatment capacity following optimization?
A. Net treatment capacity is exp3ected to be 2 million gallons
per day following optimization.
Q. What is the expected treatment capacity following expansion?
A. Net treatment capacity is expected to be 3 million gallons
per day following expansion.
Q. What is the expected treatment capacity following future (2008)
expansion?
A. The City’s net treatment capacity estimated for year 2017
is expected to be about 7.7 million gallons per day. The addition
of a new wellfield and treatment facility will account for 4.7 million
gallons per day of the total capacity. A new wellfield and treatment
facility would be implemented in phases to match the demand increase within
the service area.
Q. What steps is the City taking to reduce the amount of leakage
within its distribution system?
A. The City has an ongoing maintenance program that repairs
leaking system components as they are identified.
Q. Will the City use their surface water permit if 0.8 cfs?
A. The City does not intend to make use of the existing surface
water permit. The permit is for withdrawal in the lower reach of
Munsel Creek, where both water quality and quantity are low during late
summer when the water is most needed. Treatment of such surface water
for potable use is more difficult and costly than treatment of groundwater.
Q. If the City is successful in reducing water use by 10% as
stated in the application for the Water Use Permit, what impact will this
have on sewer rates? (Sewer rates are based on water consumption).
A. Sewer rates would not be impacted. The major reduction
would be in peak usage, primarily irrigation.
|
|
|
|
|
|
|
||
|
|
||
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
P.O. Box 1212 Florence, Oregon 97439 |
|
|