    Oak Street Bypass
    City's Plan

    Our Goal: To improve the livability of Florence through public education and community involvement.
     
    Oak Street "Extension"

    On May 15, 2000, the Florence City Council approved an application to the Oregon Department of Transportation (ODOT) for a grant of $2.142 million.  The project being proposed is something the city is euphemistically calling an "extension" of Oak Street.  According to the application, the total project will cost $3.57 million.  That means the City of Florence will be paying $1.428 million.  This amount does not include the reconstruction of the existing Oak Street stormwater system, which may not be large enough to handle more stormwater.

    The application also mentions another planned extension of Oak Street which is not addressed in this funding request:

    "Oak Street is presently constructed between 21st Street and 37th Street.  The draft Comprehensive Plan and the draft TSP include provision for the development of Oak Street between 10th and 21st Streets".
    Miller Park is located between 15th and 20th Streets. The Oak Street "right-of-way" is currently being used as a bike/pedestrian path which borders Miller Park on the east side.

    This eventual full development of Oak Street from 10th street north to 37th Street is described in the draft Comprehensive Plan and the draft Transportation Systems Plan, both of which are currently being reviewed by the City Council.
     
    Project Expense Oak - 37th to 46th (60' ROW) Oak - 46th to MLR (60' ROW) Oak - MLC to City Limits (60' ROW) Munsel Lake Road - Oak to Hwy 101 (80' ROW)
    Totals by project category
    Prelim. Engineering
    $ 130,000
    $ 80,000
    $ 40,000
    $ 90,000
    $ 340,000
    Environmental  
    25,000
       
    25,000
    Right of Way Acquisition
    360,000
    160,000
    80,000
    260,000
    860,000
    Construction
    890,000
    405,000
    200,000
    450,000 (inc. traffic signal)
    1,945,000
    Contingency (20% TO 30%)
    180,000
    90,000
    40,000
    90,000
    400,000
    Total Project Cost
    $ 1,560,000
    $ 760,000
    $ 360,000
    $ 890,000
    $3,750,000
    Notes:  Source of funds - Local Street Networks Funds, Systems Development Charges, assessments and gas tax.  Includes 40% local funds.
    Total Local Street Networks Funding Requested:  $ 2,142,000
    Source: City of Florence Staff Report to City Council
    Also see:  08/01/01 - Florence Proposes to Extend Oak Street


    City's Plan
    Maps
    Information

     
       
     
     
     
     
           
     
    Citizens For Florence
    P.O. Box 1212
    Florence, Oregon 97439
    E-mail Address: citizensforflorence@yahoo.com
    Copyright © 1998-2001 Citizens For Florence. Users may download information from this web site for personal use only.  Unauthorized copying or distribution of this site or any of its contents without the express permission of the author is expressly forbidden.