    City Contracts

    City of Florence
    Contracts with Brown and Caldwell
    Source: City of Florence
    Contract
    Date
    Project Description
    Estimated Cost
    Estimated Time for Completion
    8/20/96
    Wastewater Treatment Plant
    Although the existing wastewater treatment plant has been well maintained, some of the critical mechanical systems have been in use since the 1960s. Replacement and/or rehabilitation of some equipment is needed to maintain reliability. Localized problems with infiltration and inflow have been reported, most notably in the Old Town and north Florence areas. In addition, bypassing has occurred at the Ivy Street pump station during major flow events.

    Engineering services are required for planning, preliminary design, design, and construction related services. Specific task orders will be prepared that describe the work, include a complete scope of work, a limiting fee, and provide a schedule for the work.
    Task Order No. 1: 
    Facilities Plan
    $ 233,000
    Sewer Inspection (Task 3.5) $ 5,000
    (Note: see total estimate for Brown & Caldwell services for sewage treatment plant)
    Tasks No. 1 through 13 = 400 days
    1/23/97
    Water Facilities Plan
    Rapid growth in Florence has caused peak water demand to exceed production capacity and has made it necessary to use emergency storage capacity and to purchase water from the Heceta Water District. The product of this project will be a facilities plan that will serve as a planning document for the city as it upgrades and expands the water utility to meet the needs of the service area over the next 20 years and beyond. 

    Engineering services are required for planning, design, and construction-related services. Specific task orders will be prepared that describe the work, include a complete scope of work, a limiting fee, and provide a schedule for the work.
    Task Order No. 1 - $ 123,442
    Tasks 1 through 9 - 220 days
    9/18/97
    Wastewater Treatment Plant
    Amendment No. 1 to 8/20/96 Contract
    Client desires to expand the sanitary sewer cleaning and closed-circuit television inspection effort ...
    The Scope of Services in the Agreement is amended to provide additional routine two-pass cleaning, special heavy cleaning, and closed-circuit television inspection on sewer segments selected by city staff.
    $ 2,080
    n/a
    9/18/97
    Water Facilities Plan
    Amendment No. 1 to 1/23/97 Contract
    Client desires to expand limits of the distribution system analysis ... Amend Scope of Services to include Heceta Water District distribution system (within the study area) in the distribution system analysis. Modeling efforts for this area will include identification of current deficiencies and future distribution system needs.
    $ 1,878
    n/a
    12/2/97
    Wastewater Treatment Plant
    Amendment No. 2 to 8/20/96 Contract
    Client desires to proceed with the priliminary design phase of the project, resulting in changes in the Scope of Services ...
    Amends Scope of Services to authorize Task Order No. 2 (Add tasks 14 through18.3). Preliminary Design Project management.
    $ 164,786
    n/a
    Wastewater Treatment Plant
    Amendment No. 3 to 8/20/96 Contract
    $ 0
    n/a
    5/7/98
    Wastewater Treatment Plant
    Amendment No. 4 to 8/20/96 Contract
    Client desires to proceed with the final design phase of the project, resulting in changes in the Scope of Services ... 
    This task order describes the tasks necessary to accomplish the work of preparing the contract documents for construction of the wastewater treatment plant improvements described in the recently completed facilities plan and the preliminary design report. Collection system improvements are included in a separate task order. (Add tasks 19 through 24.3) Note, Task 20 completion contingent on identification of feasible site for facultative sludge lagoon within 120 days.
    $ 986,749
    Tasks No. 19 through 24.3 - 300 days 
    6/6/98
    Wastewater Treatment Plant
    Amendment No. 5 to 8/20/96 Contract
    Client desires to proceed with a fast-track final design phase of the collection system improvements portion of the project, resulting in changes in the Scope of Services ... 
    This task order describes the tasks necessary to accomplish the work of preparing the contract documents for construction of the Ivy Street pump station improvements and force main described in the recently completed preliminary design report. Treatment plant improvements are included in a separate task order.
    $  28,272
    90 days
    7/22/98
    Wastewater Treatment Plant
    Amendment No. 6 to 8/20/96 Contract
    Client desires to proceed with design of a sludge dewatering facility in place of the facultative sludge lagoon contained in the scope of services under Amendment 4 ...
    This task order describes the tasks necessary to accomplish the work of including design of a sludge dewatering system in the contract documents for construction of the wastewater treatment plant improvements for which the work had been defined in Task Order No. 4. Facultative Sludge Lagoon is hereby deleted from the Scope of Services ...
    $  26,434
    n/a
    9/22/98
    Stormwater Management Plan
    Growth and a changing regulatory environment have made it necessary that the City of Florence provide for long range planning to guide the management of the existing storm water conveyance system and to guide the development of new systems. The product of this project will be a comprehensive stormwater management plan to serve as a planning document for the city as it upgrades and expands the stormwater conveyance system to meet the needs of the service area over the next 20 years and beyond.
    Task Order No. 1 - $ 183,281
    720 days
    Stormwater Management Plan
    Ammendment approved by City Council 9/21
    Aerial photography with old countours digitized. The city's existing 2-5 foot contour maps would be digitized, as would new aerial photos. 
    $ 11,000
    n/a
    9/22/98
    Wastewater Treatment Plant
    Amendment No. 7 to 8/20/96 Contract
    This task order describes the tasks necessary to perform a pilot soil densification study, consisting of gathering site-specific soils information related to soil (sand) densification. The information gathered will be utilized to develop a prescriptive construction specification for the wastewater treatment plant improvements for which the work had been defined in Task Order No. 4. 
    $ 35,531
    n/a
    9/24/98
    Systems Development Charges Capacity Fee Studies:
    Water SDC
    Storm Drainage SDC
    Parks and Recreation SDC
    Streets SDC
    Cost-of-Service based Water Rates
     

    $ 8,500
    $ 9,800
    $ 9,800
    $ 9,800
    $ 8,400
    80 days
     

    80 days
    80 days

    Wastewater Treatment Plant
    9/15/97 - Estimated Total Consultant Cost 
    (See total estimate for Brown & Caldwell services ) 
    Brown & Caldwell paid to September 1997
    Consulting & engineering (12% to 14% of construction cost) plus Construction management (5% of construction cost)
    If construction cost is $15.1 million (max. estimate)

     
     
    $ 233,000
     

    $ 2,869,000

    1999-2000 Budget
    1998-1999 Budget
    Salaries
    Contracts
    Tax History

     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
     
           
     
    Citizens For Florence
    P.O. Box 1212
    Florence, Oregon 97439
    E-mail Address: citizensforflorence@yahoo.com
    Copyright © 1998-2001 Citizens For Florence. Users may download information from this web site for personal use only.  Unauthorized copying or distribution of this site or any of its contents without the express permission of the author is expressly forbidden.